Micro Generation Commissioning Verification

Micro Generation Commissioning Verification Form (<10 kW)

This commissioning verification (CVF) is required for Micro Embedded Generators applying for connection with GrandBridge Energy Inc. This document must be signed by the contractor or project electrician and the owner of the project.

Site Information

Project Address(Required)

Commissioning Test Contact Information

Name(Required)
Mailing Address(Required)

Commissioning Anti-Islanding Test

#1. Turn Off Utility-Side DG Disconnect- Verification
a) Did the inverter indicate a loss of the utility grid?(Required)
b) Did the inverter shut down as required?(Required)
c) After a loss of the utility grid, is there voltage on the output of the inverter?(Required)
#2 Turn On Utility-Side DG Disconnect - Verification
a) Did the inverter reconnect with the utility grid after 5 minutes?(Required)
b) Did the inverter return to its normal operating state?(Required)
Equipment Labelling (Lamacoid or Equivalent) - Verification
a) Is a single Line diagram present on site?(Required)
b) Do the inverter(s) and DG disconnect switch nomenclature present and match site single line diagram?(Required)
c) Is there a two sources warning sign present on site?(Required)
Inverter type generators shall be compliant with CSA Standards, CSA 22.2 No. 107.1 “General use Power Supply” and CSA 22.3 No. 9-2020 “Interconnection of distributed energy resources and electricity supply systems” and bear a certification mark recognized by the Ontario Electrical Safety Code.
• In lieu of compliance with CSA 22.3 No. 9-2020 the inverter will be deemed acceptable if it achieves UL 1741 SA (2016 or later) certification
By signing this form, the commissioning test representative and the owner of the project acknowledge that all required verifications specified under this commissioning verification form have been completed and inverter equipment meets the applicable protection requirements outlined in the Generator Protective Relay Settings section of this document.
Name of Commissioner(Required)
Name of Project Owner(Required)